| Denver
Water's All-pipes (136,377) Model (APM) For Comprehensive
Fire Flow Modeling |
 |
Denver Water (DW) serves over
1.1 million customers and supplies about 500 million gallons
per day on a maximum day basis. The DW system includes
three treatment plants, 17 major pump stations and over
160 pressure zones with over 400 pressure reducing valves.
DW's primary responsibility is to supply high quality
water to its customers at the lowest cost possible. This
article presents the interim results of DW all-pipes distribution
model fire flow analysis.
In 1997 DW began a process of creating steady-state and
extended period simulation (EPS) transmission models for
a comprehensive Capital Improvement Program (CIP). This
CIP planning was completed in late 2000. The transmission
model was expanded in a second phase by creating a steady
state all-pipes model in 2002. This more detailed model
allows hydraulic analysis of smaller distribution mains.
The current effort will transform this steady-state model
into an all-pipes EPS model. This phase will verify the
model with two system-wide tracer tests at maximum day
and fall average day conditions. The all-pipes EPS model
will allow accurate determination of detention times within
the distribution system as well as determining efficient
water quality sampling locations to meet regulatory requirements.
The EPS model will also be used to refine operational
energy requirements.
As a result, these three models will allow DW to efficiently
perform the following:
- Continual monitoring of DW's 10 year Capital Improvement
Program with the transmission models.
- Review fire flow, planned developments, pressure
zone studies and track the replacement/rehabilitation
program with the steady state all-pipes model.
- Comply with continually changing regulatory requirements
as well as improving operational efficiencies with
the EPS all-pipes water quality model.
APM Fire Flow Summary
Now that the third phase of the EPS APM is being
completed, DW began implementing fire flow analyses
using the interim steady state APM. As a coincidence,
one of the most severe droughts of the century hit Colorado,
with that along went our field testing for fire flow
availability. Fortunately, DW steady state APM verification
was completed and ready to be tested under fire.
DW began the process of assigning fire flow demands
to each of our 25,205 fire hydrants. This was a simple
process since DW had all the hydrant nodes flagged and
simply created a query to assign the demands. DW also
needed to know the available fire flow at a 20 psi residual
pressure to assist in determining rehabilitation and
replacements of our distribution system. All that was
left to do was to push a button and wait. In a demanding
test of its exceptional power and stability, the all-pipe
(136,377 pipes) H2ONET
model was run continuously more than 50,000 times and
consistently produced exceptional results in a timely
manner throughout the process, completing each run in
less than four seconds.
DW than began verification of the flows with our over
900 field results and determined that the flows and
pressures were too high. This made DW realize that the
minor losses at the fire hydrant weren't accurately
modeled and could be improved on. DW then added an equivalent
minor loss coefficient representing a 4 ½ -inch
hydrant nozzle to our fire hydrant branch lines and
re-ran the analysis. Again the analysis was successfully
run with comparatively better results.
Conclusion
With an accurately verified and validate hydraulic
model, results of a comprehensive fire flow analysis
will now allow DW to report "calculated" available
fire flows at very specific locations and minimize the
public relations nightmare of water waste during a drought
year. In the past DW would report fire flow availabilities
using field tests conducted nearby adding uncertainties
to the users needs. This also adds to DW understanding
of system weaknesses that aren't readily apparent.
This example also underscores the practical approach
of developing an APM for EPS analysis. Not only will
the EPS model be beneficial for future water quality
analysis so will the interim steady state model that
was used to develop the EPS model.

(Click to enlarge the picture)
|